Kolb Firefly
Construction
Log (Serial# FF-11-3-00074)
Builder:
Gregg Kaat
Date:
Hrs
9/21/11
Received kit
9/22/11
Kit arrives at Home
9/24/11
Inventoried parts. A couple small hardware items
missing 3.5 Hrs
Horizontal
Stabilizer
9/26/11
Began layout of ½ horizontal stab – leading edge tubing was damaged by
saw accident – ordered new stock from
Kolb 4.0 Hrs
9/27/11
Fabricated gussets for ½ Horz Stab and Vertical fin 6.0 Hrs
9/28/11
Fabricated brackets, reworked gusset radious’s, cut elevator leading
edges 5.0 Hrs
9/29/11
Cut hinges for stab and rudder – drilled holes in 6 inch ones 4.0 Hrs
9/30/11
Completed drilling all hinges – drilled horz stab brackets (225 holes
total last 2 days) 5.0 Hrs
10/2/11
Cut stab 1 inch tube, installed sleeve, riveted gussets on one
side
6.0 Hrs
10/3/11
Drilled and cleco gussets on other side 3.0 Hrs
10/4/11
Completed starboard side horz stab 5.0 Hrs
10/5/11 Cut tubing for port horz stab, drilled tubing
and gussets,
installed sleeve, installed gussets both sides 7.0 Hrs
10/6/11
Cut and installed crossmembers – Port side horz stab
completed 4.0 Hrs
Elevators
10/7/11
Laid out drawing on building table for port elevator – began upside
down first, cut trailing edge tube and 4 bottom ribs,
drilled,
cleco’d and assembled to leading edge 7.0 Hrs
10/8/11
Installed 1 rib, brought boom tube into basement 1.0 Hrs
10/10/11
Cut and cleco’d small ribs on top side 4.0 Hrs
10/11/11
Cut and formed corner braces, installed remaining rivets, deburred
and filed as necessary – completed Port Elevator 6.0 Hrs
10/12/11
Laid out starboard side elevator drawing on table, cut trailing edge
and
bottom ribs and cleco’d 5.0 Hrs
10/13/11
Cut and drilled top ribs, shaped ends and cleco’d 3.0 Hrs
10/14/11
Cut, drilled and riveted cross braces – riveted remaining ribs –
deburred and filed as necessary – completed starboard elevator
5.0 Hrs
Vertical
Stabilizer
10/17/11
Cut hole in bench to accommodate ring on tail post, laid out drawing on
table, cut tubing and brackets 6.0 Hrs
10/18/11 Drilled and cleco’d gussets, drilled
tail
post 6.0 Hrs
10/19/11 Made port side boom tube brackets –
riveted
gussets and
tail post 5.0 Hrs
10/20/11 Made starboard tube brackets –
drilled and
riveted gussets
5.0 Hrs
10/21/11
Cut and drilled cross braces – mis-drilled one
bracket and
had to make a new one. Riveted cross braces. Deburred Gussets
and tubing as necessary. Completed vert Stab.
6.0 Hrs
Rudder
10/24/11
Laid out rudder trailing edge drawing on table –
Installed
sleeve in leading edge – Formed trailing edge tubing 3.5 Hrs
10/25/11 Cut all Ribs – Drilled and cleco’d
Ribs on port
side –
shaped and deburred ends as necessary 5.0 Hrs
10/26/11 Started install of starboard side
ribs 2.5 Hrs
10/27/11 Completed install of ribs. Riveted
and
deburred 4.0 Hrs
10/28/11 Temporarily installed hinges on
starboard Horz
Stab and elevator – Began install of hinges on other one 5.0 Hrs
Rigging
the Tail
10/30/11
Installed Vert Stab on Boom Tube – installed
elevator horn bent, drilled and temporarily installed brackets – had to
remake
1 bracket that was bent wrong 8.0 Hrs
11/1/11 Attached L brackets to both Horz
stabs 1.0 Hrs
11/2/11
Began fitting Stab assy to boom tube – had to
remove ¼
inch of powder coat from each elevator horn – began making spacers
for horn assy 5.0 Hrs
11/3/11 Completed making spacers and installed
in
elevator horn assy. Leveled tail assy and prepared for wire
rigging 5.0 Hrs
11/4/11 Bent wire tangs as
required 2.0 Hrs
11/7/11 Constructed and temporarily installed
3 out of 4
tail brace cables 6.0 Hrs
11/8/11 Constructed and temporarily installed 4th
tail
brace cable 1.0 Hrs
11/9/11 Installed rudder horn and tail wheel
horn 5.0 Hrs
11/10/11 Disassembled tail assy – completed
riveting of
elevator
horns 2.0 Hrs
11/11/11 Temporarily installed rudder hinges –
alignment
was time consuming 4.0 Hrs
Ailerons
11/12/11 Laid out leading edge – drew trailing
edge on
bench –
Bent trailing edge to shape 4.0 Hrs
11/15/11 Began install of ribs 7.0
Hrs
11/16/11 Completed install of ribs and riveted
in place –
Port
Aileron complete 5.0 Hrs
11/17/11 Cut, formed, deburred and riveted
starboard
aileron trailing edge and bottom ribs 7.0 Hrs
11/18/11 Cut, formed,deburred and riveted top
ribs –
Starboard
aileron completed 6.0 Hrs
11/21/11 Cut, drilled and deburred all aileron
hinges –
128 holes
4.0 Hrs
11/23/11 Completed drilling of elevator and
rudder
hinges 5.0 Hrs
Wings
11/28/11
Cut leading and trailing edge tubes – riveted inboard rib to main
spar – set main ribs on spar 5.0 Hrs
11/29/11
Positioned ribs – drilled and cleco’d ribs to leading and trailing
edges - installed rib nose to steel inboard rib 5.0 Hrs
11/30/11
Completed riveting of main ribs – began install of drag strut
bracket 6.0 Hrs
12/1/11
Drilled and riveted drag strut bracket – cut drilled riveted drag
Strut 5.0 Hrs
12/2/11
Made wing tip gussets – installed Bow tip and bottom cross
brace 5.0 Hrs
12/3/11
Made upper cross brace gussets and installed upper cross brace –
made wing fold bracket 5.0 Hrs
12/4/11
Made and installed wing fold bracket 1.0 Hrs
12/5/11
Installed top false Ribs 6.0 Hrs
12/6/11
Installed wingtip top false ribs 4.0 Hrs
12/8/11
Installed cross braces and bottom false ribs 6.0 Hrs
12/9/11
Installed strut support bracket – Port wing completed 1.0 Hrs
12/10/11
Cut leading and trailing edge for starboard wing – installed inboard
Rib – placed main ribs on approx locations on spar 5.0 Hrs
12/12/11
Completed install of main Ribs 4.0 Hrs
12/14/11
Installed lift strut spar bracket and lift strut 4.0 Hrs
12/15/11
Installed wing bow tip and cross brace 5.0 Hrs
12/16/11
Installed upper wing tip cross brace and manufactured wing fold
bracket 2.0 Hrs
12/1711
Installed wing fold bracket 1.0 Hrs
12/19/11
Cut, formed, and cleco’d wing tip trailing edge cross braces began
install of top false ribs 6.0 Hrs
12/20/11
Completed install of top false ribs on main spar 5.0 Hrs
12/21/11
Installed wing tip false ribs – riveted wing tip trailing edge cross
braces 4.0 Hrs
12/22/11
Installed bottom false ribs and 2 out of 3 inboard rib
braces 5.0 Hrs
12/23/11
Installed strut support bracket and final inboard rib brace Starboard
wing completed 3.0 Hrs
Fuselage
1/6/12
Drilled all hinges to accept cotter pins – began drilling on tail-wheel
assembly 1.5 Hrs
1/13/12
Installed aileron U-Joint Aileron torque tube and control
stickIn cage
4.0 Hrs
1/15/12
Installed Flap actuator assembly
4.0 Hrs
1/18/12
Installed rudder pedal tangs and cable fairings 1.0 Hrs
1/21/12
Drilled and fitted nosecone to fuselage 2.0 Hrs
1/25/12
Installed floor pan and wing u-joints to cage 3.0 Hrs
2/2/12
Prepped and temporarily installed boom tube in cage 3.0 Hrs
2/4/12
Installed H brace in Boom tube 4.0 Hrs
2/7/12
Installed sling seat 5.0 Hrs
2/8/12
Temporarily installed tail wheel assm to vert stab 1.0 Hrs
2/10/12
Installed rudder cables and rigged forward end 3.0 Hrs
2/11/12
Installed elevator cables and rigged aft end 3.0 Hrs
2/13/12
Rigged forward end of elevator cables 2.5 Hrs
2/14/12
Cut and trimmed laminate for instrument panel 4.0 Hrs
2/15/12
Glued laminate to nosecone – Drilled upper holes in landing
gear 3.0 Hrs
2/17/12
Completed temp install of landing gear 2.5 Hrs
2
/20/12
Drilled holes in panel for instruments – trimmed as
necessary 3.5 Hrs
2/28/12
Fabricated center console 3.0 Hrs
3/5/12
Completed rigging of rudder cables 3.5 Hrs
3/16/12
Installed aileron hinges 4.0 Hrs
3/21/12
Rigged wings to fuselage cage 7.0 Hrs
3/22/12
Fabricated wing struts 6.0 Hrs
3/25/12
Temp installed motor mount, tailwheel, landing gear legs.
Installed wiring for wing tip strobes 3.0 Hrs
3/28/12
Temporarily installed engine for rigging – Reworked landing
gear axles and fittings 5.0 Hrs
4/3/12
Rigged ailerons – reworked fuel pump mount 6.0 Hrs
Electrical
4/7/12
Began routing wires for panel, mounted voltage regulator 4.0 Hrs
4/8/12
Iinstalled connectors for strobes, cut holes in floor pan for wiring,
completed riveting aileron horns 6.0 Hrs
4/15/12
Primed and painted floor pan, primed aileron hinges, began creating
wire harnesses, completed install of voltage regulator 8.0 Hrs
4/19/12
Sprayed topcoat on Hinges – ran flex conduit, made up wire bundles,
primed flap torque tube, installed wire connectors 8.0 Hrs
5/1/12
Completed wiring 4.0 Hrs
Covering
5/2/12
Disassembled plane to get ready for covering prep process
7.0 Hrs
5/3/12
Measured, drilled fabric rivet holes in starboard wing 6.0
Hrs
5/4/12
Measured, drilled holes in port wing – primed rudder hinges
6.0 Hrs
5/11/12
Installed anti chafe on tail surfaces and ailerons 4.0 Hrs
5/12/12
Completed fabric covering on one elevator – started the other
elevator
6.0 Hrs
5/14/12
Completed covering other elevator – started covering Horz
stab 4.0 Hrs
5/15/12
Completed one Horz stab – started other one 7.5 Hrs
5/16/12
Completed other Horz stab – started vert stab 4.0 Hrs
5/17/12
Completed bottom half of vert stab – started top 5.0 Hrs
5/18/12
Completed vert stab – started covering rudder 5.0 Hrs
5/19/12
Completed covering rudder except for trailing edge tape 7.5
Hrs
5/20/12
Installed trailing edge tape on rudder – began covering aileron
6.0 Hrs
5/22/12
Completed covering aileron – started covering other aileron
6.0 Hrs
5/23/12
Completed covering aileron – applied first coat of brush to all tail
parts and ailerons 5.5 Hrs
5
/30/12
Began installing anti chafe tape on wing 3.5 Hrs
6/2/12
From 6-2 to 6-9 completed covering starboard wing 57 Hrs
6/17/12
From 6-11 to 6-16 completed covering port wing – still need To apply
first coat of Brush to top side yet 40 Hrs
6/22/12
From 6/18-6/22 finished brush coat on top of wing – Began spray
coats of brush and poly spray on all except cage and
one
wing
half 32 Hrs
6/28/12
From 6/24 – 6/28 completed spray coats of poly spray on all but
cage and one wing half 30 Hrs
6/29/12
From 6/29--7/12 completed spray coats of poly spray and ½ done
with
finish black base coat – high heat days so mainly half
days or no
work
at all some days 24 Hrs
7/21/12
From 7/13-7/21 Completed black finish coat on tail and
other wing
half
completed
covering of cage – completed poly spray on cage 36 Hrs
7/25/12
From 7/22-7/25 completed black on cage – began trim paint on tail
surfaces
20 Hrs
7/29/12
From 7/26-7/29 went to Oshkosh
8/4/12
From 7/31-8/4 Continued trim paint on tail surfaces 28 Hrs
Rigging
8/11/12
From 8/6-8/11 completed trim on tail and cage – assembled cage boom and
tail - attached all engine sensors 36 Hrs
8/18/12
From 8/12-8/18 completed trim on wings – attached wings 42
Hrs
8/25/12
From 8/19-8/25 completed wiring strobes – attached muffler assm
and
test ran
engine – Engine kill and Grand Rapids EIS not working
correctly
– found bad ground and reworked connection –
Engine Kill and GR unit check OK now – ran through half of Engine
Break
in chart 44 Hrs
8/26/12
Completed Engine break in procedure. Ready to fly
6/22/13
Replaced bent landing gear
|